CE Service

Active Product Owner: Yerry Alberto Garita Aguilar
Priority Team Group VP Value Effort Notes
10 None None None None

Kickoff

TBD to TBD

Design

TBD to TBD

Build

01 Jan 2030 to TBD

Iterate

TBD to TBD

Projected Go Live Date

TBD
TBD

Issues

# Issue Days Passed Status
41 CE-Serv: Safety Stock Refactor #2 97 Open
40 CE-Serv: Safety Stock Updates 101 Open
39 CE-Serv: Add D Plant Codes to D Plant List 102 Open
38 Report Parsing 103 Open
37 CE-Serv: CSV Export Button 92 Open

Upcoming Milestones

Planned Date Phase Task Deadline Status

Comments

All Milestones

Phase Milestone Status Planned Date Actual Date
build Build In Progress TBD TBD