CE Returns

On Hold Product Owner: Kevin Fischer
Priority Team Group VP Value Effort Notes
40 Ben Van Den Bosch, Jim Dautzenberg, Christophe Feyen, Ena Kovalchuk, Brianna Schildgen, Rishi Matani Operations Strategy & Project Management Paul Martin None None
  • 5 Issue Tracker Tickets https://tracker.internal.prod.apps.bsci.com/project/13/issue/all/
  • Add 261 movement 
  • RGA Created not Received due June 17
  • New Issue: Add Plant Filter to Customer Owned RGA table
  • Cycle Time Enhancement - team to define requirements (target end of June) 

Kickoff

02 Apr 2020 to 08 Apr 2020

Design

13 May 2020 to 17 Jun 2020

Build

08 Apr 2020 to 30 Jun 2020

Iterate

07 Jul 2020 to TBD

Projected Go Live Date

0 minutes
April 30, 2021

Upcoming Milestones

Planned Date Phase Task Deadline Status

Comments

All Milestones

Phase Milestone Status Planned Date Actual Date
kickoff Kick-off Meeting Complete April 2, 2020 April 2, 2020
kickoff Infrastructure Set Up Complete April 8, 2020 April 8, 2020
design Feature List Complete May 13, 2020 May 13, 2020
design Wireframe Review 1 Complete May 26, 2020 May 26, 2020
design Wireframes Approved Complete June 17, 2020 June 17, 2020
build Build Sprint 1 Complete June 30, 2020 June 30, 2020
build Build Sprint 1 Complete Complete June 30, 2020 June 30, 2020
build Test Link Delivered Complete April 8, 2020 April 8, 2020
iterate Customer Feedback Review 1 Complete July 7, 2020 July 7, 2021
iterate UAT - TBD TBD
iterate Build Approved (Final Sign-Off) - TBD TBD
sustain Production Link Delivered - TBD TBD
sustain Go-Live - TBD TBD
sustain 1 Month Follow Up - TBD TBD
sustain 3 Month Follow Up - TBD TBD
sustain 6 Month Follow Up - TBD TBD
sustain Sustain Sprint 1 - TBD TBD
sustain Sustain Sprint 1 Complete - TBD TBD